Performance result

HOME >Performance result > Actual construction
 
Total 24
No. Completion date Construction title Client Capacity Location
24   12.2015   Pilot Class(10TPD), Waste Biomass incinerator System Making   CES Co., Ltd.   10ton/day   Inchoeon Metropolitan City
23   11.2016   2nd Resource recovery facility waste heat boiler reprepair construction   Saehan Environment Co., Ltd.   48ton/day   ChunAn, Kongki
22   07.2016   High temperature incinerator facility making, Installation construction   TOP Energy Solution Co., Ltd.   62.4ton/day   Hwaseong, Kyungki
21   12.2015   Daegil Green Corp. Heat energy recovery facility construction   Daegil Green Co., Ltd.   156ton/day   Inchoeon Metropolitan City
20   11.2015   Waste energy incineration heat use facility making, erection construction.   S&E Energy   92.4ton/day   Yangjoo, Kyungki
19   06.2015   Combustiom furance and steam supply facility   NRE Holdings Inc.   51.1ton/day(#2)   Asan, Chungnam
18   04.2015   Gaesung waste facility(2nd) carry-in supply and incineration facility(RK incinerator) design, erection, installation cnstruction   Hyundai Asan Inc.   25ton/day   Gaesung Industrial complex
17   12.2014   Saehan Environment Corp. Waste energy incineration heat use facility making, erection(ESCO)   Phoenix Co., Ltd.   48ton/day   CheongAn city Chungnam
16   09.2014   Dongyang Environment Inc. Solid fuel incineration boiler facility installation energy saving business(ESCO)   Peaco Inc.   93.6ton/day   SeoSan, ChungNam
15   10.2013   Heating medium boiler erection and installation construction   Samjung Pulp Co., Ltd. Pyung Taek plant   3,800,000kcal/hr   Pyung Taek, Kyungki
14   10.2013   Incinerator #2 prevention facility changing construction   Dongyang Environment Co.,Ltd.   48 TON/DAY   Deajeon
13   10.2013   Incineration facility and prevention facility erectiom and installation construction   Samjung Pulp Co., Ltd.   -   Susan, ChungNam
12   08.2013   Waste heat recovery boiler erection and installation construction   Mirae Paper Inc.   6,500KG/HR   JunJu, Chunbook
11   08.2013   SeoKwang Hi-Tech Inc. Sludge dry facility installation construction   Seokwang
Hi-tech Inc.
  Dryer 100ton/day   Susan ChungNam
10   09.2013   Thailand MSW pretreatment facility, incineration facility, and auxiliary facility design/ erection/ delivery/ installation   Daerim stainless Inc..
Hyundai heavy industry Inc..
Dohwa Engineering Inc..
  295 ton/day*
2 lot
  Thailand
9   10.2012   Incinerator, Boiler(Vertical merge type, water tube 2Drum) and prevention facility design, erection, installation construction   SamJung Pulp Co., Ltd. PyungTaek plant   72ton/day   PyungTaek, KyungKi
8   06.2012   Incinerator maintenance and prevention facility erection and installation construction   Serveone Inc.   60ton/day   Susan, ChungNam
7   04.2012   Incinerator maintenance and Boiler( water tube type, 2 Drum), White smoke prevention facility design, erection, installation construction   Bumwoo Inc.   48ton/day   Ulsan
6   12.2011   Incinerator, Boiler (Vertical merge type, water tube type 2 Drum) and prevention facility design, erection, installation construction.   Bumwoo Inc.   72ton/day   Ulsan
5   10.2011   Incinerator maintenance and boiler (water tube type, 2 Drum) design, erection, installation construction   Namkang Paper Inc.   30ton/day   Jinju, KyungNam
4   03.2011   Incinerator, Boiler(Vertical merge type, water tube type 2 drum) design, erection, installation construction   Dosi Environemnt Inc.   24ton/day   YunChun, KyungKi
3   07.2010   Incinerator, boiler( Vertical merge type, water tube type 2 Drum) and prevention facility design, erection, installation construction   Mirae Paper Inc.   24ton/day   JunJoo, JunBook
2   04.2010   Rotary kiln maintenance works   EG Inc.   -   Ulsan
1   10.2009   High temperature Bag filter facility erection and installation construction   EG Inc.   -   Ulsan
  1